Xinrong 100MW PV Combined Power Station Project-1
Project Highlights
  • The template construction is firstly adopted to unify construction standards, improve construction quality, and avoid common quality problems.
  • The electrical processes for the foundation construction of box-type transformers, cable laying, and electrical wiring are strictly controlled, and the construction quality is excellent.
  • All risks of the project are controlled in advance, and the project progress meets the requirements.
Project Name
Xinrong 100MW PV Combined Power Station Project
Project Type
General mountain PV power station + mining subsidence area
Location
Xinrong, China
Average Annual Power Generation
175,291MWh
Product Type
Double-sided half-chip module + fixed bracket
Project Highlights
  • PV power station is built in the coal mining subsidence area
  • The fully prefabricated cabin solution is adopted for the step-up substation
  • An intelligent O&M and fault diagnosis system is adopted to improve O&M efficiency.
  • The support is made of high-strength steel, and the amount of steel used for the support in the whole project is reduced by 468t.

Other Sucessful Cases Appreciation

BIPV Power Station Project
Shaanxi coal group BIPV Power Station Project
BIPV Gas Station project
Shandong PV Power Station Project

Products Related

60-cell MBB Half-cell Module (1)
72cells Bifacial PERC Half-Cell PV Module
60-cell MBB Half-cell Module (3)
72cells Bifacial PERC Half-Cell PV Module